Renovations

inside the safeToilet signPurple Glass
Before the Renovations

Images of the Old Post Office in Morrinsville, before its transformation into an Art Gallery.

5. Exterior painting4. New flooring!3. New floor
Final Renovations! Weeks 11 - 14

Sept 13th - October 8th The final month of renovations flew past in a flurry of activity, as the building ...

3. Wallace panels2. Entrance doors4. Office
Renovations: Weeks Nine and Ten

August 30th - September 10th: I've now moved into the Gallery, to my new office! It's still a building site, ...

8a. Reception1. Exterior painting7. Reception
Renovations: Weeks Seven and Eight

August 16th-27th: the interior painting is finished, the extra bits of 'solid plastering' done, the toilets ...

4. Painting8. Wallace Gallery4b. Painting
Renovations: Weeks Five and Six

August 2nd-13th: Week Five saw the removal of asbestos in the reception area ceiling, and then the painters ...

9a. Asbestos removal6. Pillar9. Asbestos removal
Renovations: Week Four

July 26th-30th: the first main phase of interior construction came to an end this week, with many details ...

9i. The Wallace view9c. inside the office8. gib board
Renovations: Week Three

July 19th-23rd: Progress continues apace, as the walls are lined with sheets of ply, then gib board (so there ...

soon to be a kitchenoutside the officethe contractors' boards
Renovations: Week Two

July 12-16th 2010, and big changes are being made to the internal wall-structure, transforming the post ...

8. new wall bones9. in the Community Gallery4. making holes
Renovations: Week One

See the blog for a more detailed description of the first week of construction on the gallery site. See ...

 